News Footage shows near-completion of new N.Korean power plantExperts unsure if plant will make May construction deadline ahead of Seventh Party Congress
North Korea have made rapid progress on a third power plant in the Mount Paekdu region, footage from Korean Central Television (KCTV) published on Tuesday shows. The footage shows that numerous parts of the third Paekdusan Youth Hero hydro plant are complete, with electricity transmission infrastructure also in place. Buildings which will likely house generator machinery and large pylons are also apparent. “Unstopping from the revolutionary spirit of finishing the exterior of the hydro plant, the workers have recently finished the construction of hydraulic turbine and hydraulic turbine dynamo room,” the KCTV broadcast says. Images from the Rodong Sinmunreleased © Korea Risk Group. All rights reserved. |